Home/Insights/TNUoS and HV sites
Guide

TNUoS charges: why high voltage (HV) sites pay more from 2026, and what to do

From April 2026, the fixed part of Transmission Network Use of System (TNUoS) charges rose by around 65% on average, and the bands sites are charged in are fixed until 2031. High voltage (HV) connected sites are among the most exposed. Here is what changed, and the options worth weighing up.

UPDATED 5 OCTOBER 2026 BY TOM WAUGH, FOUNDER & MANAGING DIRECTOR PUBLISHED 29 SEPTEMBER 2026 ENERGY PLANNER / GUIDE

What changed in April 2026

TNUoS charges pay for the national transmission network. The largest part for most business sites, the residual charge, is a fixed amount per site per day. The National Energy System Operator (NESO) charges it to suppliers, and how it shows on your bill depends on your contract: as a separate line, inside a standing charge, or built into your rates.

For 2026/27, NESO says the residual charge is on average 65% higher than in 2025/26, reflecting higher allowed transmission revenue under Ofgem's 2026 to 2031 price control (RIIO-3). NESO's current forecasts show it continuing to rise to 2031, and an updated five year view is due on 8 October 2026.

Because it is charged per site rather than per unit, using less electricity does not reduce it. What decides the charge is the band a site falls into, set by its connection voltage and agreed capacity. Sites without an agreed capacity are banded on annual consumption.

Why HV sites are most exposed

The options

Do the numbers before the engineering

Metering relocation is widely promoted. Sometimes it is the right answer. On some sites a capacity review may be enough, provided the reduction is large enough to qualify for a band change. We look at the bill, the connection agreement and the half hourly data first, then set out which routes are worth a closer look.

What a proper feasibility study looks at

Relocating the metering from HV to LV changes the TNUoS band, but it is not a free saving. Some costs move in the other direction, and a credible study nets them off first:

The output you should expect is a net figure over the price control period, an indicative payback, a clear view on whether to proceed, and a list of the information still needed. If a proposal only shows the TNUoS saving, it is worth asking what has been left out.

How metering relocation works

Many high voltage sites own the transformers, switchgear and cables between the grid connection and their buildings. Relocation moves the point of metering to the low voltage side of that equipment, so the site is charged in a low voltage band.

This is usually done through network adoption, where a licensed independent network operator takes over the high voltage equipment. Where adoption applies:

What the process looks like

Timings vary by site. To start a feasibility review we usually need a recent single line diagram of the site's electrical network (or the nearest equivalent), recent bills or consumption data, your connection agreement and access for a short site visit.

Judge it on the net figure

A good assessment sets the reduction in transmission charges against the higher distribution charges and transformer losses that come with low voltage metering, and shows the net result over the price control period. We have seen some strong examples, with projected net savings running into six figures for larger sites, but the result varies a lot from site to site.

How Energy Planner helps

Common questions

Can I reduce TNUoS charges by using less electricity?
Not the residual part. It is a fixed charge per site per day based on your charging band, so it does not fall with consumption. The band itself is what you need to look at.

Can my site move to a lower charging band?
Sometimes. Bands are set by connection voltage and agreed capacity, or by consumption where there is no agreed capacity. Before 2031, a band change generally needs a change of more than 50% in capacity or consumption, or a change in connection voltage, and each option needs assessing properly.

Does metering relocation cost anything upfront?
Often very little or nothing. Where the high voltage equipment is adopted by a licensed network operator, the works and upgrades can usually be included in the adoption. A feasibility review confirms this for your site.

How long does it take?
Typically around three to five months from the first site audit to switchover, depending on the site, the equipment and the network operator.

Is metering relocation right for every HV site?
No. It depends on the site's load, the existing equipment and the cost of the works against the saving over the price control period. A feasibility review comes first.

Is your site high voltage connected?

Leave your details for a free, no obligation initial review. We will check your charging band and whether metering relocation or a capacity review is worth a closer look.

No obligation. We only use your details to respond to this enquiry and never sell your data. See our privacy notice.

Thank you

We have your details and will be in touch within one working day.

High voltage site?

Send us a recent bill and we will tell you which band you are in and whether any of the options are worth a closer look.

Book a call

Sources: NESO final TNUoS tariffs 2026/27, NESO 2026/27 tariffs webinar and Ofgem DCP410 decision. This page is general information based on published charging methodologies and tariffs as at October 2026, not advice on your specific sites. Charges, bands and forecasts change, and any physical works need a proper feasibility study, so it is worth confirming the position for your sites before making a decision.

High voltage site?

Send us a recent bill and we will tell you which band you are in and whether any of the options are worth a closer look.